Large Construction Activities

(Primary and Secondary Operators)

Construction Storm Water Program Construction Storm Water Program
A primarmy operator of a large construction activity must apply for coverage under the TPDES TXR150000 general permitand submit a Notice of Intent (NOI). Operators (primary or secondary) of these sites are required to complete the following:
  • Develop a Storm Water Pollution Prevention Plan (SWPPP)  according to the provisions of the TPDES TXR150000 that covers the entire site or all portions of the site for which the applicant is the operator. The SWPPP must be submitted to DPW-ENV for review within 5 days of receiving the notice to proceed.  The SWPPP must be approved, prior to commencing construction activities.
  • Submit a Notice of Intent (NOI) – Primary Operators only, using a form provided by the Texas Commission on Environmental Quality (TCEQ), at least 7 days prior to commencing construction activities if submitted by mail. If submitted electronically, the NOI must submit an NOI to the TCEQ prior to commencing construction activities. Primary operators must complete a Primary Operator Construction Site Notice (CSN) using a form provided by the TCEQ.
  • Secondary operators must complete a Secondary Operator Construction Site Notice (CSN) using a form provided by the TCEQ.
  • Post signed copies of the primary operator’s NOI at the construction site prior to commencing construction activities in a location where it is readily available for viewing by the public. The NOI must be maintained in that location until the completion of the construction activity.
  • Post copies of all operator’s CSNs at the main entrance of the construction site. The notice must list the general permit number (or a copy of the NOI), the name and telephone number of a representative for the operator, a brief description of the project, and the location of the SWPPP.
  • Provide copies of the signed and certified NOI and CSNs to DPW-ENV at least 14 days prior to the commencement of construction activities. Storm Water Pollution Prevention Plan (SWPPP)
    Mail to:
    Directorate of Public Works
    Environmental Division
    Attn: IMSW-HOD-PWE
    Bldg. 4622 Engineer Drive
    Fort Hood, TX 76544-5028
  • Follow all provisions set forth in the Construction Site Storm Water Inspection Program Memorandum of Instruction (MOI)dated November 12, 2008.
  • Primary Operators must submit a Notice of Termination (NOT), using a form provided by the TCEQ when the site has reached Final Stabilization.
  • When the project has been temporarily stabilized and is being closed out call DPW-Environmental for a Final Closure Inspection at 254-287-6499.
  • Secondary Operators must date their CSN of when it was removed and notify the MS4 operator.
WARNING This is a Department of Defense (DoD) interest computer system. All DoD computer systems are subject to monitoring at all times to ensure proper functioning of including security devices, to prevent unauthorized use and violations of statutes and security regulations, to deter criminal activity, and for other similar purposes. If monitoring of this or any other DoD computer system reveals possible evidence of violation of criminal statutes, this evidence and any other related information, including identification information about the user may be provided to law enforcement officials.